![]() |
The NGEx Resources Inc. website is at www.ngexresources.com.
Information Links: Yahoo News and Quotes | MB | StockCharts
This report is based on NI 43-101 resource and reserve disclosures and fully diluted share counts available on 2009-09-24.
The GoldMinerPulse metrics, presented below in table format, are based on all projects and all in situ metals and are updated daily with closing market prices.
| General Metric | Value on 2013-05-23 |
|---|---|
| In Situ Metal Value per Share (MVpSh) | US$225.76 |
| Average Ore Value per Tonne | US$35.03 |
| Metal Value Leverage (MVL) | -no stock price- |
| Market Capitalization as a Percentage of Metal Value | - price unavailable |
| Recent Closing Stock Price | C$ [note 1] |
| Fully Diluted Share Count | 134.16 M [note 2] |
| Percentage In Situ Proven + Probable Reserve | 0% |
| Percentage In Situ Measured + Indicated Resource | 28% |
| Percentage In Situ Inferred Resource | 72% |
| Metric | Value on 2013-05-23 |
|---|---|
| Gold Reserves + Resources | 6.39 M oz |
| Average Gold Ore Grade | 0.2 g/t |
| Market Capitalization per oz of Gold In Situ | US$0.00 ( C$0.00 ) |
| Gold Equivalent Ounces Estimate | 21.74 M oz |
| Market Capitalization per oz of Gold Equivalent | US$0.00 ( C$0.00 ) |
Note 1: Conversion rate used: 1 Cnd$ = 0.971426 US$
Note 2: Fully diluted share count taken from NGEX Resources Inc., Investor Information web page (viewed September 2009)
All metal counts in this section are based on the combined Proven + Probable reserves plus the Measured + Indicated and Inferred resources.
| Metric / Metal | Gold | Silver | Copper | Zinc | ||
|---|---|---|---|---|---|---|
| Total Counts (reserves + resources) | 6.39 M oz | 8.40 M oz | 2.79 M t | 536.55 K t | ||
| Metal Prices in US$ (from 2013-05-23) | $1,392.90 / oz | $22.66 / oz | $3.29 / lb | $0.82380 / lb | ||
| Metal Value per Share (MVpSh) Shown in US$. Based on fully diluted share count | $66.37 | $1.42 | $150.71 | $7.26 | ||
| Percentage of Total Metal Value | 29.40% | 0.63% | 66.76% | 3.22% | ||
| Metal Value Percentage Proven + Probable | 0% | 0% | 0% | 0% | ||
| Metal Value Percentage Measured + Indicated | 35% | 28% | 24% | 45% | ||
| Metal Value Percentage Inferred | 65% | 72% | 76% | 55% | ||
The above metal value totals derive from the following projects.
| Project | Location | Metal Value per share (% total) | Average Ore Value US$/t | Gold | Silver | Copper | Zinc | PP% | MI% | I% |
|---|---|---|---|---|---|---|---|---|---|---|
| Josemaria | San Juan, Argentina | $130.66 ( 57.9% ) | US$38.11 | 3.25 M oz | 1.79 M t | 0 | 0 | 100% | ||
| GJ Kinaskan Donnelly | British Columbia, Canada | $71.63 ( 31.7% ) | US$25.50 | 2.97 M oz | 2.83 M oz | 747.45 K t | 0 | 73% | 27% | |
| Hambok | Western Eritrea, Eritrea | $23.46 ( 10.4% ) | US$113.64 | 172.65 K oz | 5.57 M oz | 249.36 K t | 536.55 K t | 0 | 43% | 57% |
PP%: percentage of metal value from Proven + Probable reserves
MI%: percentage of metal value from Measured + Indicated resources
I%: percentage of metal value from Inferred resources
Note: percentages may no add to 100% due to rounding errors
Latest NI43-101 Report: TECHNICAL REPORT ON THE GJ COPPER-GOLD PORPHYRY PROJECT LIARD MINING DIVISION BRITISH COLUMBIA, CANADA
2007-04-30 (134 pages).
Project Location: British Columbia, Canada. View Google Map.
Average Ore Value (all estimate types): US$25.50
Indicated
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $22.28 | 2.15 M oz | 0.262 g/t | 254.74 M t |
| Copper | $30.13 | 557.88 K t | 2,190.000 g/t | 254.74 M t |
Estimate notes: See NI 43-101 p. 10 of 134, Table 1 Summary of Giroux estimates
0.05 % Cu Cut-off
Inferred
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $3.42 | 329.35 K oz | 0.210 g/t | 48.78 M t |
| Copper | $4.61 | 85.37 K t | 1,750.000 g/t | 48.78 M t |
Estimate notes: "See NI 43-101 p. 10 of 134, Table 1 Summary of Giroux estimates";
0.05 % Cu Cut-off
Inferred
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $5.09 | 490.72 K oz | 0.208 g/t | 73.38 M t |
| Silver | $0.48 | 2.83 M oz | 1.200 g/t | 73.38 M t |
| Copper | $5.63 | 104.20 K t | 1,420.000 g/t | 73.38 M t |
Estimate notes: See NI 43-101 p. 11 of 134, Table 3 for GJ Kinaskan Donnelly North;
0.05 % Cu Cut-off
Latest NI43-101 Report: Hambok Deposit, Mogoraib Exploration License, Gash-Barka District, Western Eritrea 43-101 Technical Report and Preliminary Resource Assessment
2009-01-23 (102 pages).
Project Location: Western Eritrea, Eritrea.
Average Ore Value (all estimate types): US$113.64
Indicated
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $0.71 | 68.80 K oz | 0.200 g/t | 10.70 M t |
| Silver | $0.40 | 2.35 M oz | 6.840 g/t | 10.70 M t |
| Copper | $5.66 | 104.86 K t | 9,800.000 g/t | 10.70 M t |
| Zinc | $3.26 | 240.75 K t | 22,500.000 g/t | 10.70 M t |
Estimate notes: See Table 19: Indicated Resource within the Mineralized Shell on p. 76 of 102 in the NI 43-101 dated January 2009.
Cutoff 0.75 %Zn
Inferred
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $1.08 | 103.85 K oz | 0.190 g/t | 17.00 M t |
| Silver | $0.54 | 3.22 M oz | 5.890 g/t | 17.00 M t |
| Copper | $7.80 | 144.50 K t | 8,500.000 g/t | 17.00 M t |
| Zinc | $4.00 | 295.80 K t | 17,400.000 g/t | 17.00 M t |
Estimate notes: See Table 20: Inferred Resource within the Mineralized Shell on p. 76 of 102 in the NI 43-101 dated January 2009.
Cutoff 0.75% Zn
[Source: xxxx]
Latest NI43-101 Report: Preliminary Resource Estimate Update
for the Josemaria Project,
San Juan Province, Argentina
2007-11-20 (206 pages).
Project Location: San Juan, Argentina.
Average Ore Value (all estimate types): US$38.11
Inferred
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $33.78 | 3.25 M oz | 0.220 g/t | 460.00 M t |
| Copper | $96.88 | 1.79 M t | 3,900.000 g/t | 460.00 M t |
Estimate notes: See Table 16.8: Total Resource, 2007 Resource Model, Josemarķa. on p. 117 of 206 in the NI43-101 dated November, 2007.
0.3% TCu cutoff