Rio Alto's primary focus for 2010 will be to build and operate a dump leach gold mine at La Arena in Peru.
On July 20, 2010, the company received approval for its Environmental Impact Study, which had been submitted in September 2009. With the EIA, the company has access to US$24.25M of funding for development. Quoting, CEO Alex Black:
Receipt of environmental approval and the awarding of the civil construction contract represent two major milestones in the La Arena development process. We have been extremely pleased with the responsiveness of the various government agencies during the EIA approval process and are encouraged by the support for the development of La Arena demonstrated by the local communities. We are also pleased to have selected a consortium of the caliber of G&M and Stracon as our civil construction contractor and look forward to working with them in bringing La Arena into production.
The Rio Alto Mining Limited web site is at www.rioaltomining.com.
Information Links: Yahoo News and Quotes | Yahoo Message Board | StockCharts | Stockhouse
More Information Links: RIOAF on the OTCQX | Check RIO Lima Quotes (US$) | Rio Alto Merger Conference Call Transcript, May 28, 2009 | Canadian Insider Trading | Candlestick Analysis |
Rio Alto Fair Market Share Price Estimate updated daily.
|
This report is based on NI 43-101 resource and reserve disclosures and fully diluted share counts available on 2010-09-02.
The GoldMinerPulse metrics, presented below in table format, are based on all projects and all in situ metals and are updated daily with closing market prices.
| General Metric | Value on 2010-09-02 |
|---|---|
| In Situ Metal Value per Share (MVpSh) | US$115.93 |
| Average Ore Value per Tonne | US$34.68 |
| Metal Value Leverage (MVL) | 122.13 |
| Market Capitalization as a Percentage of Metal Value | 0.8% |
| Recent Closing Stock Price | C$1 [note 1] |
| Fully Diluted Share Count | 134.51 M [note 2] |
| Percentage In Situ Proven + Probable Reserve | 0% |
| Percentage In Situ Measured + Indicated Resource | 61% |
| Percentage In Situ Inferred Resource | 39% |
| Metric | Value on 2010-09-02 |
|---|---|
| Gold Reserves + Resources | 4.31 M oz |
| Average Gold Ore Grade | 0.3 g/t |
| Market Capitalization per oz of Gold In Situ | US$29.59 ( C$31.18 ) |
| Gold Equivalent Ounces Estimate | 12.46 M oz |
| Market Capitalization per oz of Gold Equivalent | US$10.25 ( C$10.79 ) |
Note 1: Conversion rate used: 1 Cnd$ = 0.949244 US$
Note 2: Fully diluted share count updated based on counts given at Share Structure web page (viewed September 2010).
All metal counts in this section are based on the combined Proven + Probable reserves plus the Measured + Indicated and Inferred resources.
| Metric / Metal | Gold | Copper | ||
|---|---|---|---|---|
| Total Counts (reserves + resources) | 4.31 M oz | 1.34 M t | ||
| Metal Prices in US$ (from 2010-09-02) | $1,251.30 per oz | $3.46130 per lb | ||
| Metal Value per Share (MVpSh) Shown in US$. Based on fully diluted share count | $40.14 | $75.79 | ||
| Percentage of Total Metal Value | 34.62% | 65.38% | ||
| Metal Value Percentage Proven + Probable | 0% | 0% | ||
| Metal Value Percentage Measured + Indicated | 65% | 59% | ||
| Metal Value Percentage Inferred | 35% | 41% | ||
The above metal value totals derive from the following projects.
| Project | Location | Metal Value per share (% total) | Gold | Copper | PP% | MI% | I% |
|---|---|---|---|---|---|---|---|
| La Arena Sulphide | La Libertad, Peru | $107.29 ( 92.5% ) | 3.39 M oz | 1.34 M t | 0 | 58% | 42% |
| La Arena Oxide | La Libertad, Peru | $8.64 ( 7.5% ) | 929.03 K oz | 0 | 98% | 2% |
PP%: percentage of metal value from Proven + Probable reserves
MI%: percentage of metal value from Measured + Indicated resources
I%: percentage of metal value from Inferred resources
Note: percentages may no add to 100% due to rounding errors
Latest NI43-101 Report: La Arena Project, Peru Technical Report
2008-06 (0 pages).
Updates: Reserves and resource figures taken from Peru .:. La Arena Project .:. Resource & Reserves web page viewed January 2010.
Project Location: La Libertad, Peru. View project on a Google Map.
Indicated
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $8.50 | 913.72 K oz | 0.490 g/t | 58.00 M t |
| Silver | $0.02 | 167.83 K oz | 0.090 g/t | 58.00 M t |
Estimate notes: See Peru .:. La Arena Project .:. Resource & Reserves.
Cuttoff is 0.15g/t Au.
This Valuation Report is prepared assuming that
Inferred
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $0.14 | 15.30 K oz | 0.280 g/t | 1.70 M t |
| Silver | $0.00 | 19.13 K oz | 0.350 g/t | 1.70 M t |
Estimate notes: See notes for Indicated.
Cuttoff is 0.15 g/t Au.
Latest NI43-101 Report: La Arena Project, Peru Technical Report
2008-06 (0 pages).
Updates: Reserves and resource figures taken from Peru .:. La Arena Project .:. Resource & Reserves web page viewed January 2010.
Project Location: La Libertad, Peru.
Indicated
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $17.77 | 1.91 M oz | 0.270 g/t | 220.00 M t |
| Copper | $44.93 | 792.00 K t | 3,600.000 g/t | 220.00 M t |
Estimate notes: See Peru .:. La Arena Project .:. Resource & Reserves.
Cuttoff is 0.1% Cu.
This Valuation Report is prepared assuming that
Inferred
| Metal | MVpSh | Contained Metal Quantity | Ore Grade | Ore Quantity |
|---|---|---|---|---|
| Gold | $13.73 | 1.48 M oz | 0.270 g/t | 170.00 M t |
| Copper | $30.86 | 544.00 K t | 3,200.000 g/t | 170.00 M t |
Estimate notes: See notes for Indicated.
Cuttoff is 0.15 g/t Au.
|
|
![]() |